Breaux Tide – BWTS Retrofit

Engineering and Prefabrication →

On-Site Mechanical Installation  →

On-Site Electrical Installation →

Final Testing and Preparation for Commissioning →

Ballast Water Treatment System (BWTS) Installation

Client:

Tidewater

Year:

2025

Vessel type:

Multi-purpose vessel

Class:

ABS Class

SOW:

Turnkey engineering, prefabrication support, mechanical and electrical installation

  • 20

    Installation days

  • 6

    team members

  • 0

    Days downtime

Client context

Tidewater, one of the world’s largest offshore vessel operators, required their vessels to comply with the IMO D-2 and USCG ballast water discharge standards.

The Breaux Tide was scheduled for BWTS retrofitting during a limited dry-dock window at Bollinger Shipyard, USA, in March 2025.

Maintaining Tidewater’s fleet readiness while ensuring full regulatory compliance was critical.

The Challenge

  • Tight space constraints: Integrating the BWTS system into the cargo room with minimal disruption.
  • Dry-dock time pressure: Completing a complex installation within a strict three-week timeframe.
  • Mechanical and electrical complexity: Managing a multidisciplinary scope within a confined area and coordinating multiple subcontractors safely.

BRIEF

The work to be done

project phases

  • Develop the full engineering package, including 3D scans, collision checks, system layout, spool fabrication drawings, and foundations. 
  • Prefabricate critical spools and supports. 
  • Supervise mechanical and piping installation, including removal of old systems. 
  • Manage the full electrical installation, cabling, and panel setup. 
  • Conduct functional testing and deliver the project ready for commissioning. 
Breaux Tide BWTS GLO Marine VMS Group

PROJECT SOLUTION

Implementation steps

01

Engineering and prefabrication

  • Full 3D scanning, collision analysis, system modeling. 
  • Prefabrication of spools, custom foundations for filters, UV chamber, control panels. 
02

On-Site Mechanical Installation

  • Removal of obsolete pipes.  
  • Installation of BWTS piping and equipment foundations.  
  • Mechanical installation of the filter, UV chamber, pumps, flowmeters, valves and air piping.  
03

On-Site Electrical Installation

  • Mounting and connection of electrical cabinets. 
  • Routing and connection of high-voltage cables and instrumentation (UV sensors, flowmeters, transmitters). 
  • Installation / connection of control systems and valve actuators. 
04

Final Testing and Preparation for Commissioning 

  • Hydrostatic pressure testing of pipework. 
  • Air leak testing for pneumatic systems. 
  • Final visual inspection and delivery of complete installation dossiers. 
litera-o

End of delivery

The outcomes

Final results

  • Retrofit completed within 20 days, without any dry-docking extension. 
  • 100% compliance with ABS class and IMO D-2/USCG BWTS discharge standards. 
  • Zero Lost Time Incidents (LTIs) recorded during the project. 
  • Immediate readiness for commissioning with no outstanding corrective actions. 

Through this project, GLO Marine successfully delivered a complete BWTS installation turnkey solution— from detailed engineering and prefabrication, to mechanical and electrical installation, to project supervision, testing, and full client handover.  Our ability to offer a  single-point-of-contact EPCI service  allowed Tidewater to benefit from faster execution, minimized vessel downtime, and a fully compliant retrofit process ready for final commissioning. This project reinforces GLO Marine’s role as a trusted strategic partner for large-scale, multi-vessel retrofit programs across the offshore energy sector.