Our dedicated Project Manager carefully laid out all installation works over the 25 days installation window, with clear quotas and KPIs for each day and handed over the project plan to our Installation Supervisor, who boarded the Bourbon Front together with 5 Pipe fitters and 1 Electrician to execute the job.
During installation, our on-board Installation Supervisor reported the real progress made against the forecasted schedule, at the end of each day, information which was shared with our Client for transparency and clarity.