Mezzanine Deck Prefabrication

Client Confidential
Year 2023

Vessel type
 OSV 

Class
 DNV

17t
Mezzanine deck structure

4
weeks execution time  

4
days delivery time

CLIENT CONTEXT
Mezzanine deck for diving equipment

The project brief mandated the incorporation of a mezzanine deck on the OSV for the mobilization of diving equipment. 

GLO Marine was tasked with prefabricating and delivering the mezzanine deck to the destination yard. 


THE CHALLENGE
Ensuring accuracy in prefabricated modules

The challenge in this project was that our surveyors had to closely monitor the process to ensure adherence to all design specifications and guarantee product accuracy across 3 modules 

Each deck module has been prefabricated and shipped independently. 


THE WORK TO BE DONE
Project phases
  • 17 tones of steel structure were distributed across three modules 

  • Closely monitored the prefabrication stage 

  • Ensure adherence to all design specifications and guarantee product accuracy 

  • All relevant certificates(materials, quality, and welders) were provided to Pan Marine for validation